US-69 Roadway improvements in Muskogee County JP 27108(04)
US-69 Roadway improvements in Muskogee County JP 27108(04)
This project includes roadway improvements and bridge construction along approximately 2.5 miles of US-69 in Muskogee, beginning just north of the SH-165 interchange and extending north. Work will include preparing and leveling the roadway, improving drainage, and paving the road.
Project Overview
The Oklahoma Department of Transportation (ODOT) is making improvements along approximately 2.5 miles of US-69 in Muskogee, beginning about half a mile north of the SH-165 interchange and extending north.
The project includes roadway reconstruction, drainage improvements, paving, and bridge work. Construction will take place in two major phases, with traffic shifts and temporary detours necessary to safely complete the improvements.
Construction Begins October 30, 2026
Construction is scheduled to begin Friday, October 30, with the demolition of the former railroad and pedestrian bridge located just north of Border Avenue.
Demolition is expected to continue through the weekend, with work scheduled to be completed by 5 a.m. Monday, November 2, 2026.
Traffic Impact: US-69 traffic will be temporarily rerouted using a designated detour during bridge demolition. Drivers should follow posted detour signs, allow extra travel time, and use caution when traveling through the area.
Construction Schedule and Phases
The project is divided into two major construction phases, with a total contract duration of approximately two years.
Phase 1: Roadway Improvements Near Haddock Drive
Location: From approximately Haddock Drive to just north of the former railroad/pedestrian bridge.
Estimated Contract Duration: 435 days
During this phase, crews will reconstruct portions of US-69 while maintaining traffic through the construction area.
Construction activities will include:
Initial Traffic Shifts: Northbound and southbound traffic will move to the outside lanes while crews prepare temporary connections between roadways.
Southbound Roadway Construction: Traffic will be shifted to allow crews to reconstruct the southbound lanes.
Northbound Roadway Construction: Once the southbound lanes are complete, traffic will shift again while crews reconstruct the northbound lanes.
Final Roadway Improvements: Traffic will return to the newly constructed four-lane roadway as crews remove temporary pavement connections and complete final grading.
Phase 2: Roadway Improvements Near Border Avenue and Okmulgee Avenue
Location: From just north of Border Avenue to just south of Okmulgee Avenue.
Estimated Contract Duration: 300 days
During this phase, crews will continue roadway reconstruction and improvements while adjusting traffic patterns to accommodate construction.
Construction activities will include:
Temporary Roadway Widening: Crews will prepare additional pavement to accommodate traffic during construction.
Traffic Pattern Changes: Northbound and southbound traffic will be shifted as crews construct temporary roadway connections and center pavement.
Northbound Roadway Construction: Traffic will be redirected while crews reconstruct the northbound lanes.
Southbound Roadway Construction: Traffic will shift to the completed northbound roadway while crews reconstruct the southbound lanes.
Final Improvements: Traffic will return to its designated lanes as crews remove temporary connections, install the raised center median, and complete final grading.
What Drivers Can Expect
Throughout construction, drivers should anticipate:
Temporary lane closures and changing traffic patterns
Traffic shifts between northbound and southbound lanes
Reduced speeds and construction equipment near the roadway
Temporary detours during certain construction activities
Motorists are encouraged to pay attention to posted signs, use caution in work zones, and allow additional travel time.
Stay Informed
Construction schedules and traffic impacts may change due to weather, site conditions, and other factors. Updates will be provided as construction progresses to help drivers plan ahead.
Please note: Construction timelines are preliminary estimates based on the contractor's current schedule and are subject to change.